Level II scour analysis for Bridge 37 (CABOTH00410037) on Town Highway 41, crossing the Winooski River, Cabot, Vermont Level II scour analysis for Bridge 37 (CABOTH00410037) on Town Highway 41, crossing the Winooski River, Cabot, Vermont
This report provides the results of a detailed Level II analysis of scour potential at structure CABOTH00410037 on Town Highway 41 crossing the Winooski River (also referred to as Coit’s Pond Brook), Cabot, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation...
Authors
Robert H. Flynn, Laura Medalie
Level II scour analysis for Bridge 53 (CHESTH01180053) on Town Highway 118, crossing the Williams River, Chester, Vermont Level II scour analysis for Bridge 53 (CHESTH01180053) on Town Highway 118, crossing the Williams River, Chester, Vermont
This report provides the results of a detailed Level II analysis of scour potential at structure CHESTH01180053 on Town Highway 118 crossing the Williams River, Chester, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour
Authors
Lora K. Striker, Laura Medalie
Level II scour analysis for Bridge 13 (PFRDTH00030013) on Town Highway 3, crossing Furnace Brook, Pittsford, Vermont Level II scour analysis for Bridge 13 (PFRDTH00030013) on Town Highway 3, crossing Furnace Brook, Pittsford, Vermont
This report provides the results of a detailed Level II analysis of scour potential at structure PFRDTH00030013 on Town Highway 3 crossing Furnace Brook, Pittsford, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour
Authors
Robert H. Flynn, Laura Medalie
Level II scour analysis for Bridge 12 (SUNDFLR0030012) on Forest Land Road 3, crossing Roaring Branch Brook, Sunderland, Vermont Level II scour analysis for Bridge 12 (SUNDFLR0030012) on Forest Land Road 3, crossing Roaring Branch Brook, Sunderland, Vermont
This report provides the results of a detailed Level II analysis of scour potential at structure SUNDFLR0030012 on Forest Land Road (FLR) 3 (FAS 114) crossing Roaring Branch Brook, Sunderland, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993)...
Authors
Robert H. Flynn, Laura Medalie
Level II scour analysis for Bridge 43 (SPRICYBRIG0043) on Bridge Street, crossing the Black River, Springfield, Vermont Level II scour analysis for Bridge 43 (SPRICYBRIG0043) on Bridge Street, crossing the Black River, Springfield, Vermont
This report provides the results of a detailed Level II analysis of scour potential at structure SPRICYBRIG0043 on Bridge Street crossing the Black River, Springfield, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour
Authors
Michael A. Ivanoff, Laura Medalie
Level II scour analysis for Bridge 4 (MAIDTH00070004) on Town Highway 7, crossing Cutler Mill Brook, Maidstone, Vermont Level II scour analysis for Bridge 4 (MAIDTH00070004) on Town Highway 7, crossing Cutler Mill Brook, Maidstone, Vermont
This report provides the results of a detailed Level II analysis of scour potential at structure MAIDTH00070004 on Town Highway 7 crossing the Cutler Mill Brook, Maidstone, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I...
Authors
Lora K. Striker, Laura Medalie
Science and Products
Filter Total Items: 75
Level II scour analysis for Bridge 37 (CABOTH00410037) on Town Highway 41, crossing the Winooski River, Cabot, Vermont Level II scour analysis for Bridge 37 (CABOTH00410037) on Town Highway 41, crossing the Winooski River, Cabot, Vermont
This report provides the results of a detailed Level II analysis of scour potential at structure CABOTH00410037 on Town Highway 41 crossing the Winooski River (also referred to as Coit’s Pond Brook), Cabot, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation...
Authors
Robert H. Flynn, Laura Medalie
Level II scour analysis for Bridge 53 (CHESTH01180053) on Town Highway 118, crossing the Williams River, Chester, Vermont Level II scour analysis for Bridge 53 (CHESTH01180053) on Town Highway 118, crossing the Williams River, Chester, Vermont
This report provides the results of a detailed Level II analysis of scour potential at structure CHESTH01180053 on Town Highway 118 crossing the Williams River, Chester, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour
Authors
Lora K. Striker, Laura Medalie
Level II scour analysis for Bridge 13 (PFRDTH00030013) on Town Highway 3, crossing Furnace Brook, Pittsford, Vermont Level II scour analysis for Bridge 13 (PFRDTH00030013) on Town Highway 3, crossing Furnace Brook, Pittsford, Vermont
This report provides the results of a detailed Level II analysis of scour potential at structure PFRDTH00030013 on Town Highway 3 crossing Furnace Brook, Pittsford, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour
Authors
Robert H. Flynn, Laura Medalie
Level II scour analysis for Bridge 12 (SUNDFLR0030012) on Forest Land Road 3, crossing Roaring Branch Brook, Sunderland, Vermont Level II scour analysis for Bridge 12 (SUNDFLR0030012) on Forest Land Road 3, crossing Roaring Branch Brook, Sunderland, Vermont
This report provides the results of a detailed Level II analysis of scour potential at structure SUNDFLR0030012 on Forest Land Road (FLR) 3 (FAS 114) crossing Roaring Branch Brook, Sunderland, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993)...
Authors
Robert H. Flynn, Laura Medalie
Level II scour analysis for Bridge 43 (SPRICYBRIG0043) on Bridge Street, crossing the Black River, Springfield, Vermont Level II scour analysis for Bridge 43 (SPRICYBRIG0043) on Bridge Street, crossing the Black River, Springfield, Vermont
This report provides the results of a detailed Level II analysis of scour potential at structure SPRICYBRIG0043 on Bridge Street crossing the Black River, Springfield, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour
Authors
Michael A. Ivanoff, Laura Medalie
Level II scour analysis for Bridge 4 (MAIDTH00070004) on Town Highway 7, crossing Cutler Mill Brook, Maidstone, Vermont Level II scour analysis for Bridge 4 (MAIDTH00070004) on Town Highway 7, crossing Cutler Mill Brook, Maidstone, Vermont
This report provides the results of a detailed Level II analysis of scour potential at structure MAIDTH00070004 on Town Highway 7 crossing the Cutler Mill Brook, Maidstone, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I...
Authors
Lora K. Striker, Laura Medalie